Road to Uttarakhand village on LAC with China by year-end: Govt | India News

Uttarakhand village that called poll boycott to get road ‘in 8 months’
DEHRADUN: After a long wait, Dumak might get a road by the year-end. After TOI reported Thursday that the 250-odd voters in Dumak had decided to boycott polls over the promised road, Uttarakhand Rural Roads Development Agency (URRDA) CEO Kamrendra Singh issued a statement saying pending work on the road will be completed in eight months, reported.
URRDA said the delay in building a road to the remote village, situated at 6,000ft altitude, in Chamoli district was due to “change in alignment because of landslides in the area”.
After a long wait, Dumak might get a road by the year-end. After TOI reported Thursday that the 250-odd voters in Dumak had decided to boycott polls over the promised road, Uttarakhand Rural Roads Development Agency (URRDA) CEO Kamrendra Singh issued a statement saying pending work on the road will be completed in eight months, reports Pankul Sharma.
URRDA said the delay in building a road to the remote village, situated at 6,000ft altitude, in Chamoli district was due to “change in alignment because of landslides in the area”.
Road to Uttarakhand village on LAC with China by year-end: Government
The under-construction road connecting Dumak and other villages in Chamoli district along the Indo-China border in Uttarakhand, which has been delayed time and again even 17 years after the project was launched, will be completed before the year ends, authorities promised in a written statement on Thursday.
Taking cognizance of a report published in TOI on Thursday, which highlighted how the 250-odd voters in Dumak have decided to boycott LS polls after being fed up of constant delays on the road construction, Uttarakhand Rural Roads Development Agency CEO Kamrendra Singh issued a statement saying the pending work will be completed in the next eight months. He claimed that the delay was due to “change in alignment because of landslides in the area.”

The statement, signed by CEO and the agency’s chief engineer Ravi Singh, stated that construction on the first 20.5km stretch & the 23 to 29km stretch have been completed, with work on four connecting lanes ongoing. However, construction of a bridge in the middle of the two has been delayed due to it being in a landslide zone.
Officials added that landslides in 2018 and 2021 necessitated changes in the alignment . However, there was disagreement among villagers over the proposed changes.